Aerial view of Phillips 66 Terminal
Warehouse / Logistics·Probable

Phillips 66 Terminal

Estimated MW
21.0
 
Score
94
 
Nearest sub.
138 kV
0.3 mi away

Signal profile

Power100Grid proximity95Voltage class70Footprint100Underutilization82Data confidence100
  • Power60% of score100
    21.0 MW est.Footprint × archetype W/m²
  • Grid proximity25% of score95
    0.3 mi to substationHIFLD / SeerAI substations 2025
  • Voltage class15% of score70
    138 kV nearestHIFLD transmission
  • Footprint100
    129.6 acresOSM building footprint
  • Underutilization82
    WARN-corroboratedTX WARN layoff notices
  • Data confidence100
    100% fields · enrichedField coverage

Axes marked “% of score” are the weighted components of the headline composite (94). The rest are corroborating context.

Intelligence

The Phillips 66 Terminal is a strong candidate for a small data center or container-BESS deployment due to its underutilized power capacity and proximity to a high-voltage substation. The key risk lies in potential logistical and permitting challenges associated with repurposing an industrial site. The site's probable tier designation and corroboration of underutilization support its candidacy.

The Phillips 66 Terminal is a logistics and warehouse facility with an estimated load of 20.97 MW, suggesting underutilization of its potential power capacity. Given its proximity to a 138 kV substation, just 0.27 miles away, the site is well-positioned for a container-BESS or edge data center deployment, which could capitalize on existing grid interconnection and provide a new revenue stream. The facility's single-story, large area, and probable tier designation indicate a potential for repurposing or co-location, but the primary risk lies in navigating the complexities of industrial site redevelopment and ensuring compliance with relevant regulations.

Underutilization signals

  • Wood Group USA Inc. · Freeport, Brazoria County, TX180 layoffs · 2025-01-05T00:00:00.000

Location

Coordinates
28.93531, -95.33576
Archetype
Warehouse / Logistics
Confidence tier
Probable
Estimated load
21.0 MW