Manufacturing·Probable
Unnamed Manufacturing
3500 West Lake Street Melrose Park
Estimated MW
12.1
Score
64
Nearest sub.
69 kV
670.0 mi away
Signal profile
- Power60% of score9212.1 MW est.Footprint × archetype W/m²
- Grid proximity25% of score10670.0 mi to substationHIFLD / SeerAI substations 2025
- Voltage class15% of score4069 kV nearestHIFLD transmission
- Footprint765.0 acresOSM building footprint
- Underutilization82WARN-corroboratedTX WARN layoff notices
- Data confidence80100% fieldsField coverage
Axes marked “% of score” are the weighted components of the headline composite (64). The rest are corroborating context.
Underutilization signals
- Millwood, Inc. · 5000 Proviso Dr Ste 1, Melrose Park, IL 60163underutilization_warn
Location
Coordinates
41.89637, -87.87699
Archetype
Manufacturing
Confidence tier
Probable
Estimated load
12.1 MW